Denmark

Denmark

Gallery: Klim Fjordeholme repowering

DENMARK: Vattenfall is repowering the 21MW Klim Fjordeholme project in northern Denmark, replacing the Vestas 600kW turbines with Siemens' 3.2MW machines.

  • Vattenfall dismantled the old 21MW Klim Fjordeholme in the early summer of 2014

    Vattenfall dismantled the old 21MW Klim Fjordeholme in the early summer of 2014

  • The 35 Vestas V40 600kW wind turbines had been in operation since 1996

    The 35 Vestas V40 600kW wind turbines had been in operation since 1996

  • The old turbines have been sold for recycling in Italy and Ireland, among other countries

    The old turbines have been sold for recycling in Italy and Ireland, among other countries

  • Vattenfall used 1,125kg of dynamite to remove the existing foundations

    Vattenfall used 1,125kg of dynamite to remove the existing foundations

  • The 13,000 tonnes of concrete was crushed so it can be reused in construction of new roads

    The 13,000 tonnes of concrete was crushed so it can be reused in construction of new roads

  • New 22 Siemens 3.2MW turbines with a hub height double the original turbines are being installed

    New 22 Siemens 3.2MW turbines with a hub height double the original turbines are being installed

  • When complete, Klim will become the largest onshore wind farm in Denmark, at 70.4MW

    When complete, Klim will become the largest onshore wind farm in Denmark, at 70.4MW

of

The Klim Fjordeholme project entered operation in 1996. It used 35 Vestas V44 600kW turbines, which Vattenfall dismantled in 2014. 

The turbines have been sold for reuse at projects in Ireland, Italy and other countries, Vattenfall said. 

In their place 22 Siemens 3.2MW turbines have been installed with a hub height of 94 metres — more than double the old turbines hub height, which stood at 40 metres.

The new turbine has a 130-metre diameter rotor compared with the Vestas turbines' 44-metre rotor.

All of the concrete foundations had to be removed or replaced. Vattenfall said it used 1.1 tonnes of dynamite to remove the concrete and steel bases. The concrete was then crushed to be reused for road construction, while the steel was melted down to be recycled.

The repowered Klim project is due for completion in 2016 and will become Denmark's largest onshore wind project. 

Pictures courtesy of Michael Bo Rasmussen/Vattenfall.

Have you registered with us yet?

Register now to enjoy more articles
and free email bulletins.

Sign up now
Already registered?
Sign in