The German manufacturer will deliver nine MM92 2.05MW turbines to the North Steads project near Widdington, Northumberland.
Delivery is expected in April 2016, and the project will be commissioned in September 2016. The turbines will be installed at a hub height of 78.5-metres.
Senvion will then service the project for five years, with the option to extend a further five.
Senvion said it was the second contract it had won from Infinis in the UK. In November 2014, Infinis chose Senvion to provide 12 MM92 and nine MM100 turbines to the 43MW A'Chruach wind project in Scotland.
It is also Senvion's second UK order in October, having won a contract from developer Blue Energy. Senvion will supply ten 3.4M0-102 and 22 3.4M-114 turbines to the Beinneun project in the Scottish Highlands. This is Senvion's largest UK order to date.