Germany

Germany

Gallery: Wpd's 288MW Butendiek is online

GERMANY: This week, German developer Wpd put its 288MW Butendiek offshore project online as all 80 Siemens turbines were connected.

  • wpd has completed the 288MW Butendiek offshore project in the North Sea

    wpd has completed the 288MW Butendiek offshore project in the North Sea

  • All 80 Siemens 3.6MW turbine have been connected to the grid

    All 80 Siemens 3.6MW turbine have been connected to the grid

  • Power produced from the project will be transmitted to the grid via the SylWin1 link

    Power produced from the project will be transmitted to the grid via the SylWin1 link

of

The 288MW wind farm has been under construction since March 2014, 32 kilometres west of the German island of Sylt in the North Sea. It seen total investment reach €1.3 billion. 

Monopole installation was completed in July 2014 in water depths ranging from 17 to 22 metres. Design of the foundations was carried out in-house by contractor Ballast Nedam Engineering, while other aspects of construction and logistics were handled by Ballast Nedam Offshore.

Installation of the project was delayed briefly in July 2014. A construction worker was injured by a snapped cable after it became trapped under a vessel. The injured man spent six weeks in hospital.

The first of 80 Siemens 3.6MW tubines was installed in September 2014, with first power being exported to the German grid in February 2015.

Butendiek is connected to the German grid via the SylWin1 grid connection, which was commissioned by Siemens in April. The link also serves Vattenfall's 288MW DanTysk project. 

The project is jointly owned by developer Wpd, investment firms Marguerite Fund, Siemens Financial Services, Industriens Pension (IP), Pensionskassernes Administration (PKA),  CDC Infrastructure, and Swiss utility Ewz. 

Have you registered with us yet?

Register now to enjoy more articles
and free email bulletins.

Sign up now
Already registered?
Sign in