Giants in the forest

German-Danish company Nordex has installed the first two N80 2.5 MW wind turbines to come off its commercial production line for megawatt machines. The turbines have gone up in Germany at the Mahlberg wind station near Freiburg in the inland state of Baden-Württemberg.

"Installation was a challenge," admits the company, a subsidiary of Borsig Energy. The N80 weighs a total 330 tonnes and the nacelle and hub alone 110 tonnes. A prototype N80 has been tested for a year at the Grevenbroich wind test field in North Rhine Westphalia.

A sharp incline to the 500 metre-high site in the Black Forest meant that machine house components had to be transported individually and assembled on site. The blades were comparatively light at 8.6 tonnes each, but their 40 metre length required dexterity from the crane operator to get them lifted from the road and swung vertically onto the forest track.

Have you registered with us yet?

Register now to enjoy more articles
and free email bulletins.

Sign up now
Already registered?
Sign in

Before commenting please read our rules for commenting on articles.

If you see a comment you find offensive, you can flag it as inappropriate. In the top right-hand corner of an individual comment, you will see 'flag as inappropriate'. Clicking this prompts us to review the comment. For further information see our rules for commenting on articles.

comments powered by Disqus

Windpower Monthly Events

Latest Jobs