Overlapping offshore projects cause dilemma

GERMANY: Competing project applications from overlapping sites in the German Baltic Sea have created transmission headaches for the regulator.

Overlapping projects create transmission headache for regulator
Overlapping projects create transmission headache for regulator

Germany's permitting authority the Bundesamt für Seeschifffahrt und Hydrographie (BSH) was tasked with drawing up the region's first offshore transmission network plan.

Three project clusters have been outlined in the first draft of the Bundesfachplan Offshore 2013 for the Baltic Sea. But identifying each cluster's capacity "cannot...be done on the basis of applications to the BSH", states the draft document.

Cluster 1 is located within the Westlich Adlergrund offshore wind priority area and so far features two permitted projects; E.on's 480MW Arkona Becken Südost and Iberdrola's 400MW Wikinger. BSH has estimated an eventual total cluster capacity of 1.7GW.

By contract, Cluster 2 is not in a priority zone for offshore wind, but several applications have been submitted. BSH has allocated it a cluster capacity of 1.3GW.

A third and final cluster, Kriegers Flak, has been awarded development priority. BSH has earmarked a total capacity of 722MW. One project is already well-progressed, EnBW's Baltic 2, while there are two competing applications in the southern part of the zone.

Each cluster currently features proposed projects whose sites overlap each other, notes the plan. Given that competing projects have yet to be awarded development rights, it is not possible to calculate total cluster capacity.

BSH has instead used the average area per turbine quoted in Baltic Sea applications and compared this with North Sea permitted projects, in order to arrive at a theoretical "turbines per cluster" number. This is then multiplied by an assumed capacity per turbine of 7MW.

The formula has resulted in average density of two turbines per square kilometre and a total capacity in the German Baltic Sea of just under 3.7GW.

Before commenting please read our rules for commenting on articles.

If you see a comment you find offensive, you can flag it as inappropriate. In the top right-hand corner of an individual comment, you will see 'flag as inappropriate'. Clicking this prompts us to review the comment. For further information see our rules for commenting on articles.

comments powered by Disqus
[DAYS_LEFT] days Subscribe Now

Left of your Windpower Monthly free trial

Your free trial Subscribe Now

to Windpower Monthly has expired

Windpower Monthly Events

Search more than 4,500 companies in the Windpower Directory

Latest Jobs