Vestas receives 128MW California order

UNITED STATES: Vestas has won a 128MW order from the Sacramento Municipal Utility District (SMUD) for an extension to its Solano project near Rio Vistas, California.

Vestas V90 1.8MW and 3MW turbines make up the order
Vestas V90 1.8MW and 3MW turbines make up the order

The deal is for 24 V90 3MW and 31 V90 1.8MW turbines, which will be built at Solano 3. Delivery is planned for the second half of 2011, with the project set to come online in 2012.

Vestas turbines are in use on the other two parts of the project. Solano 1 uses 23 Vestas V47 660KW and Solano 2 uses 29 V90 3MW turbines.

Most of the order will be manufactured in the US, apart from the V90 3MW nacelles which will be built in Denmark.

Speaking in 2008 about the benefits of a utility owning a wind project, SMUD spokesman Jon Bertolino said:  "We have certainly found that owning the project site produces economic advantages for us. We're actually able to own it and operate it cheaper than what we're seeing on the open market."

Before commenting please read our rules for commenting on articles.

If you see a comment you find offensive, you can flag it as inappropriate. In the top right-hand corner of an individual comment, you will see 'flag as inappropriate'. Clicking this prompts us to review the comment. For further information see our rules for commenting on articles.

comments powered by Disqus
Only [DAYS_LEFT] days Subscribe Now

Left of your Windpower Monthly free trial

Your free trial Subscribe Now

to Windpower Monthly has expired

Windpower Monthly Events

Search more than 4,500 companies in the Windpower Directory

Latest Jobs